Tuesday 13 May 2008

Lazarian World Homes Update


Today we were able to complete stacking the foam blocks up to four feet high on four different buildings in preparation for the pouring of cement. We also have prepared two more building foundations to be poured tomorrow. We have dealt with many issues regarding our tools and trailers getting cleared into the country. We're also having problems wiring funds to the U.S. for our concrete purchases, which seemed to be an easy task but quickly became complicated. Pray for those two issues as we continue to try to resolve them. Also, if you could pray for the safety of our work team and the progress of our work. Our objective is to completely build 8 buildings in two months with volunteer labor.

I'm reminded daily of Psalms 127:1 "Unless the Lord builds the house, its builders labor in vain."

-Kenn

No comments: